Planning and managing Hinkley Point C
Contents |
[edit] Introduction
In early-2017, the Institution of Civil Engineers (ICE) hosted a networking evening with EDF Energy to discuss project planning for Hinkley Point C, the first nuclear power station in the UK in over a generation and the largest infrastructure project of the decade.
The evening featured presentations from David Speight, EDF Energy’s Head of Civil Construction, Nuclear New Build and Sarah Williamson, Laing O’Rourke Technical Director. The presentations were sought to answer some of the pressing questions the industry has regarding the project.
[edit] How can the project be delivered on cost and on time?
David Speight highlighted that previous experience of developing nuclear power plants in France meant that EDF was able to formulate a strong set of project values and culture based on lessons learned.
These values all stem from an overriding focus on quality and aim to ensure that humility, respect, solidarity, positivity and clarity permeate through the workforce. In order to facilitate this, each meeting starts with a safety message that focuses on previous examples of accidents onsite.
This approach has seen some success, as in December 2016, the Hinkley Point construction team (HPC) was able to confirm that they had one million man hours without lost time for injury.
[edit] How can HPC mitigate making construction errors onsite?
Sarah Williamson contextualised the enormity of the project by explaining that the joint venture between Bouygues and Laing O’Rourke (BYLOR) will have to produce 50 million bent bars, equivalent to the number of grass blades on three tennis courts.
She said that was why it was imperative there are no mistakes onsite as it cannot be built twice. To limit construction errors in the first instance, BYLOR decided designs need to be 3D, clash-free and buildable onsite.
In order to achieve this, they have been employing 3D modelling allowing designers to build each component of the plant virtually as many times as they need to, before creating a design they can guarantee will be successful onsite.
This approach will not only account for lowering onsite errors only but also increase efficiency rates and reduce the likelihood of health and safety issues.
[edit] What are the next steps in the project?
Both speakers stressed that in less than 50 days they will be laying the first concrete of the first nuclear new build of this generation, already a critical project milestone.
In 2017, they also have the following objectives to complete:
- Start of HPC site accommodation campus.
- First safety-related concrete used in gallery.
- Completion of east welfare building.
- Handover of civil works design studies for reactor pre-stressing gallery.
- Handover of civil works design studies for pumping station raft.
- Start installation of seawater cooling pipes.
EDF and Laing O’Rourke mentioned the importance of limiting errors. For further knowledge on health and safety see the Management of Contractors as part of ICE's health and safety series.
The EDF evening was part of ICE’s Energy, Resilience and Climate Change campaign.
This article was originally published here by ICE on 22 February 2017. It was written by Claire Miller.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Timber in Construction Roadmap
Ambitious plans from the Government to increase the use of timber in construction.
ECA digital series unveils road to net-zero.
Retrofit and Decarbonisation framework N9 launched
Aligned with LHCPG social value strategy and the Gold Standard.
Competence framework for sustainability
In the built environment launched by CIC and the Edge.
Institute of Roofing members welcomed into CIOB
IoR members transition to CIOB membership based on individual expertise and qualifications.
Join the Building Safety Linkedin group to stay up-to-date and join the debate.
Government responds to the final Grenfell Inquiry report
A with a brief summary with reactions to their response.
A brief description and background to this new February law.
Everything you need to know about building conservation and the historic environment.
NFCC publishes Industry White Paper on Remediation
Calling for a coordinated approach and cross-departmental Construction Skills Strategy to manage workforce development.
'who blames whom and for what, and there are three reasons for doing that: legal , cultural and moral"
How the Home Energy Model will be different from SAP
Comparing different building energy models.
Mapping approaches for standardisation.
UK Construction contract spending up at the start of 2025
New construction orders increase by 69 percent on December.
Preparing for the future: how specifiers can lead the way
As the construction industry prepares for the updated home and building efficiency standards.
Embodied Carbon in the Built Environment
A practical guide for built environment professionals.